Question: For a project with the following details, compute the completion time and identify the critical/non-critical activities with their slack values. Activity Immediate Predecessors Duration (days)
For a project with the following details, compute the completion time and identify the critical/non-critical activities with their slack values.
Activity
Immediate Predecessors
Duration (days)
A
-
1
B
A
4
C
A
2
D
A
2
E
D
3
F
D
3
G
E
2
H
F,G
1
I
C,H
3
J
B
2