Question: For a software development project, the estimated project completion time is 1 2 weeks with a standard deviation of 1 . 5 weeks. Determine the

For a software development project, the estimated project completion time is 12 weeks with a standard deviation of 1.5 weeks. Determine the due date for the project with a 95% confidence level. (Ans: 14.48)