Question: For Activity 1, the earliest starting (ES) time is ? For Activity 2, the earliest finishing (EF) time is ? For Activity 3, the latest

For Activity 1, the earliest starting (ES) time is ?
For Activity 2, the earliest finishing (EF) time is ?
For Activity 3, the latest (LF) time is ?
For Activity 4, the latest starting (LS) time is?
For Activity 5, the earliest finishing (EF) time is ?
For Activity 6, the earliest starting (ES) time is ?
For Activity 7, the latest finishing (LF) time is ?
For Activity 8, the latest starting (LS) times is?
For Activity 9, the earliest finishing (EF) time is ?
The slack time of Activity 2 is ?
The slack time of Activity 4 is ?
The slack time of Actuvity 7 is?
The slack time of activity 8 is ?
The slack time of Activity 9 is ?
For Activity 1, the earliest starting (ES) time
Number Activity 1 2 3 4 5 6 7 Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work Predecessor 1 1 2,3 2,3 5 4,6 Duration Estimates (a, m, b) 2, 3, 6 months 1, 2, 3 months 1, 1, 2 months 2, 3, 6 months 1, 1, 2 months 1, 1, 2 months 1, 1, 3 months

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!