Question: For Activity j - k: Latest Start Time = 1 2 d Duration = 6 d ? Earliest Finish Time = 1 7 d ?

For Activity j-k:
Latest Start Time =12d
Duration =6d?
Earliest Finish Time =17d?
For Activity j-y:
Latest Start Time =17d?
()
Earliest Finish Time =18d?
Question(s)
Determine: Latest Finish Time for Node j.
 For Activity j-k: Latest Start Time =12d Duration =6d? Earliest Finish