Question: For an activity in a CPM analysis, the Early Finish time is 8 and the Late Finish time is 1 0 . Which of the

For an activity in a CPM analysis, the Early Finish time is 8 and the Late Finish time is 10. Which of the following statements is true?
Question 9 options:
a)
The slack for this activity is 2.
b)
The duration of this activity is 2.
c)
The late finish time is 12.
d)
The activity is on the critical path