Question: 3. For an activity in a CPM analysis, the early finish time is 34 and the late finish time is 34. Which of the following

3. For an activity in a CPM analysis, the early finish time is 34 and the late finish time is 34. Which of the following statements is true? a. The slack for this activity is 34. b. The activity is on the critical path. c. The activity's early start is 0. d. The duration of this task is 34. e. The activity's late start must happen before its early start