Question: For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10 . The activity duration is


For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10 . The activity duration is 4 days. Which of the following statements is true? Multiple Choice The late finish is 14. The early finish is 12 . The slack for this activity is 2 . The activity is not on the critical path All of the Above