Question: For an activity in a CPM analysis, the early start time is 8 and the late start time is 1 0 . Which of the
For an activity in a CPM analysis, the early start time is and the late start time is Which of the following statements is true?
Multiple Choice
The late finish is
The early finish is
The slack for this activity is
The duration of this activity is
The activity is on the critical path.