Question: For an activity with duration t, slack can be calculated as a. LS-ES O b. LF-t O c. LS+t O d. LS+ES Which activities have

For an activity with duration t, slack can beFor an activity with duration t, slack can beFor an activity with duration t, slack can be

For an activity with duration t, slack can be calculated as a. LS-ES O b. LF-t O c. LS+t O d. LS+ES Which activities have slack in the following diagram? start B 3 E 1 finish {A 4 C 2 D7 F2 a. B, E o b. B, D, E O C. A, C, D, F o d. A, C, D, E Critical activities are distinguished by the presence of a. zero slack. O b. slack. C. wasted time. o d. idle resources