Question: For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish ( EF ) time?

For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time?
Group of answer choices
the largest EF among the immediate predecessors.
the average EF among the immediate predecessors.
the largest LF among the immediate predecessors.
the difference in EF among the immediate predecessors.