Question: For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish ( EF ) time?
For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish EF time?
Group of answer choices
the largest EF among the immediate predecessors.