Question: - For an established small office building , you are assigned as a PM to plan for installation of the following systems to renovate the

- For an established small office building, you are assigned as a PM to plan for installation of the following systems to renovate the building by delivering a Green Structure. You have selected different sub-contractors to perform their independent identified tasks during the estimated times specified for them. Please plan the best and shortest time you suggest to complete the job? Please show the best start & finish schedules of work for each subcontractor to produce minimum slack, by showing the activities on a Gantt chart.

Solar Panel installation & necessary circuitry 6 working days

Changing windows 12 days

Modify HVAC system & internal coil to take

Advantage of Solar system 18 days

Change all electrical bulbs to LED lighting 4 days

Complete painting job of the office 10 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!