Question: For each activity, you are given its optimistic time, its most likely time, and its pessimistic time, in that order. Times are in days. OM/EM331-HW3-S23
For each activity, you are given its optimistic time, its most likely time, and its pessimistic time, in that order. Times are in days. OM/EM331-HW3-S23 a) What is the expected path duration of each path? (10 points) b) What is the standard deviation of each path? (10 points) c) What is the probability that the project can be completed in 44 days or less? ( 5 points) d) What is the probability that the project will require more than 49 days to be completed? ( 5 points)