Question: For each of the following networks diagram, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity
For each of the following networks diagram, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity times.
a. AOA diagram
b. AON diagram
c. AOA diagram
1 10 2 3 8 4 5 6 5 7 4 7 8 9 2 5 N 10 11 w 12 5 1 18 2 13 3 3 4 10 5 11 7 6 9 8 9 1 10 14 3 4 2 3 8 15 11 14 8 7 6 9 10 5 13 6 13 11 13 14 6 12 3 10 15 16
Step by Step Solution
There are 3 Steps involved in it
Networking technique is used to plan schedule and control different projects such as construction works design and installation of systems maintenance ... View full answer