Question: For the following network diagram, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity times. AON
For the following network diagram, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity times.
AON diagram
.png)
2 9 9 8 4-6 5 2 3
Step by Step Solution
3.48 Rating (181 Votes )
There are 3 Steps involved in it
Calculate the activity and the project duration from the AON diagram as below In order to determine the project schedule the planned starting time and ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1019-B-C-A-C-P-A(2143).docx
120 KBs Word File
