Question: For each of the negative project risks listed below, identify a corresponding positive risk if the opposite condition were to be true. For instance, a

For each of the negative project risks listed below, identify a corresponding positive risk if the
opposite condition were to be true.
For instance, a delayed delivery from a supplier could delay the project. However an early
delivery from that supplier could accelerate the project.
1. A new stakeholder adds an additional requirement to the project that extends the project
and adds $50,000 additional cost.
2. Industry conditions change resulting in a shortage of suppliers with a key component needed
on the project. This leads to less competition and higher costs from suppliers.
3. An unexpected test failure forces a redesign, causing a delay and overrun to the project.
4. Due to a promotion, a Core Team member leaves the team and a new person joins the team.
It takes the new person several weeks to get up to speed causing a project delay and several
activities must be reworked.
5. A schedule conflict with another project for the use of shared equipment needed to
complete some project activities causes a delay.
6. Over allocation of resources may lead to a shortage of resources for key project tasks.
7. Your project is funded by a customer and the customers funding source is reduced forcing
you to descope or cancel you project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!