Question: For Earned Value Management, BCWP - BCWS is _ _ _ . Question 3 3 options: Schedule performance index Schedule variance Cost variance Cost performance
For Earned Value Management, BCWP BCWS is
Question options:
Schedule performance index
Schedule variance
Cost variance
Cost performance index