Question: For Earned Value Management, BCWP - BCWS is _ _ _ . Question 3 0 options: Cost variance Schedule performance index Cost performance index Schedule

For Earned Value Management, BCWP - BCWS is ___.
Question 30 options:
Cost variance
Schedule performance index
Cost performance index
Schedule variance