Question: For every day the evaluation is completed earlier than the normal schedule, there is a $1,000 bonus. 1. Draw a network diagram with forward/backwards pass.

For every day the evaluation is completed earlier than the normal schedule, there is a $1,000 bonus. 

1. Draw a network diagram with forward/backwards pass. 

2. What is the critical path and expected completion time of the project? 

3. Which activities to crash and what is the total cost? 

4. How much bonus money was earned? 

Activity Immediate Predecessor(s) NT (days) CT (days) Crash Cost/day A -- 6 

Activity Immediate Predecessor(s) NT (days) CT (days) Crash Cost/day A -- 6 6 -- B A 10 8 $500 C 5 4 $300 D C 4 1 $700 E D 9 7 $600 F B, E 2 1 $800