Question: For Example 1 2 . 4 , suppose that the programmers choose not to obtain additional help to complete the project; that is , Bonner
For Example suppose that the programmers choose not to obtain additional help to complete the project; that is Bonner will code the modules without outside assistance.aInwhat way will this alter the project network and the precedence constraints?bFind thecritical path of the project network you obtained in part a How much longer is itthan the one determined in Example