Question: For Example 1 2 . 4 , suppose that the programmers choose not to obtain additional help to complete the project; that is , Bonner
For Example suppose that the programmers choose not to obtain additional help to complete the project; that is Bonner will code the modules without outside assistanc. aIn what way will this alter the project network and the precedence constraints? b Find thecritical path of the project network you obtained in part a How much longer is it than the one determined in Example