Question: For example, if a task takes 3 weeks, you can put two people on it for one week and complete it in 2 weeks at
For example, if a task takes 3 weeks, you can put two people on it for one week and complete it in 2 weeks at a cost of $100. If a task takes 5 weeks, you can put two people on it for one week to reduce it to 4 weeks at a cost of $100 or you can put two people on it for two weeks to reduce it to 3 weeks at a cost of $200. When the costs of crashing two tasks are the same, you should crash the earliest task first.
To reduce the duration to 11 weeks, which task will you crash?
A.
Task A
B.
Task C
C.
Task D
D.
Task F
What is the minimum cost of crashing this project to 11 weeks?
A. $100
B. $150
C. $200
D. There is no additional cost.
Is there now a second critical path?
A. Yes
B. No
To reduce the duration another week (from 11 weeks to 10 weeks), which task(s) will you crash? (You are again following the rules of the Project Management Game.)
A. Task F
B. Tasks C and B
C. Tasks F and L
D. Tasks C and F
What is the additional cost of crashing this project from 11 weeks to 10 weeks?
A. $100
B. $150
C. $200
D. $300