Question: For forward pass calculations, If there are two activities as predecessors to a single activity, choose the one with the [ which scheduling time ]
For forward pass calculations, If there are two activities as predecessors to a single activity, choose the one with the which scheduling time to become the ES day to insert into the successor activity.
For backward pass calculations, When there are two successor activities backing into a single activity, choose the one with the which scheduling time day to become the LF day to insert into the predecessor activity.
Maximum amount of time an activity can be delayed without delaying the early start of any other activity
Float an activity may have, subject to use by other activitiesalso called shared float
the sequence of activities which, when their durations are summed determines the minimum duration of the project
AoN and AoA Diagrams are what type of modeling technique?
FinishtoFinish, StarttoFinish and Start. toStart are what type of activity relationship found on a network diagram?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock