Question: For one specific project, the estimated average time for the critical path is 120 days. The standard deviation along the critical path is 8. Please
For one specific project, the estimated average time for the critical path is 120 days. The standard deviation along the critical path is 8. Please choose the correct answer by using PERT analysis.
3. What is the probability that the project can be completed between 116 and 124?