Question: For output to equal projected demand, what should be the actual cycle time for this production line? A ) 5 4 seconds B ) 2

For output to equal projected demand, what should be the actual cycle time for this production line?
A)54 seconds
B)27 seconds
C)20 seconds
D)18 seconds
E)14 seconds
For output to equal projected demand, what is the minimum number of workstations needed?
A)6
B)4.5
C)3
D)2.7
E)2
For output to equal projected demand, perform line balancing using the rule(most followers) and tie breaker (longer task time). What will be the efficiency of the production line?
A)90%
B)95%
C)97%
D)99%
E)100%
For output to equal projected demand, what will be the first task performed at the third workstation of the production line?
A)u
B)v
C)w
D)**
E)y
 For output to equal projected demand, what should be the actual

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!