Question: For Part 2 of the Final Project, develop two Gantt Charts using Instagantt ( one for Organizing a Race and another for the Software Data

For Part 2 of the Final Project, develop two Gantt Charts using Instagantt (one for Organizing a Race and another for the Software Data Processing project). Below are two tables detailing the specific activities associated with the "Organizing a Race" and "Software Data Processing" projects. The tables contain data that you are instructed to include in your completed Gantt Charts. Enter the activities, durations, and predecessors under "Normal" conditions.
Organizing a Race Project Data for Gantt Chart
\table[[Activity,Description,Normal Time in Days],[1,Finalize sites & contracts,28],[2,Select race promoter,14],[3,Hire Race Manager,21],[4,Design Promotional Website,25],[5,Target entertainment,45],[6,Set venue capacity,3],[7,Identify On-site fundraising,6],[8,Finalize sponsors,35],[9,\table[[Define & place signage for],[sponsors]],8],[10,Sign Concession Contracts,32],[11,Secure Merchandise sales,25],[12,Purchase Race awards,48],[13,Develop site plan,31],[14,Hire Security Director,20],[15,Hire Support Staff,17],[16,\table[[Develop police/fire security],[plan]],55],[17,\table[[Develop Traffic Plan]],20],[18,\table[[Determine Reqmts for Power],[& Facilities]],30],[19,\table[[Install],[Power/plumbing/AC/Toilet],[Svcs]],6],[20,\table[[Ready for Race]],1]]
 For Part 2 of the Final Project, develop two Gantt Charts

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!