Question: For risks that have occurred in a project, the team should Group of answer choices track and document the risks and store the information in
For risks that have occurred in a project, the team should Group of answer choices track and document the risks and store the information in lessons learned. add more resources to the tasks that are impacted by the risk occurring. talk about the risk without recording the minutes of the meeting. expect that the other risks are going to occur so they should increase resources for those tasks impacted