Question: For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened. b-1. Which activities in order of

 For the data shown, reduce the project completion time by three

For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened. b-1. Which activities in order of reduction would be shortened? A-G-DD-G-AG-D-AD-B-C b-2. Find the resulting cost to crash