Question: For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened. ACTIVITY NORMAL TIME NORMAL COST CRASH

For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.
ACTIVITY NORMAL
TIME NORMAL
COST CRASH TIME CRASH COST
A 5 $ 7,0003 $ 13,000
B 1012,000718,000
C 85,00077,000
D 64,00055,000
E 73,00066,000
F 46,00037,000
G 47,00039,000