For the following construction project, the indirect cost is estimated to be $250/day. The relationships among the
Fantastic news! We've Found the answer you've been seeking!
Question:
For the following construction project, the indirect cost is estimated to be $250/day. The relationships among the seven activities and their time-cost data are given below. Find the crashing alternative that will minimize the sum of direct and indirect costs.