Question: For the following construction project, the indirect cost is estimated to be $250/day. The relationships among the seven activities and their time-cost data are given
For the following construction project, the indirect cost is estimated to be $250/day. The relationships among the seven activities and their time-cost data are given below. Find the crashing alternative that will minimize the sum of direct and indirect costs.
1 B F A B D E F 2 C A 3 5 D Option 1 Option 2 Activity Duration Cost Duration Cost 4 E Option 3 Duration Cost (day) (S) (day) ($) (day) ($) 192 19,200 176 20,000 160 21,600 32 2,880 24 4,480 64 25,600 48 35,200 48 2,240 32 3,200 80 5,760 64 7,840 216 21,600 208 23,200 192 24,960 6
Step by Step Solution
3.45 Rating (165 Votes )
There are 3 Steps involved in it
To determine the crashing alternative that will minimize the sum of direct and indirect costs for the construction project we first need to understand the critical path The critical path is the sequen... View full answer
Get step-by-step solutions from verified subject matter experts