Question: The Texas Electronics Company (TEC) is contemplating a research and development program encompassing eight major projects. The company is constrained from embarking on all projects
The Texas Electronics Company (TEC) is contemplating a research and development program encompassing eight major projects. The company is constrained from embarking on all projects by the number of available scientists (40) and the budget available for projects ($300,000).
Following are the resource requirements and the estimated profit for each project:
.png)
a. What is the maximum profit, and which projects should be selected?
b. Suppose that management decides that projects 2 and 5 are mutually exclusive. That is, TEC should not undertake both. As a result, what are the revised project portfolio and the revised maximum profit?
c. Suppose that management also decides to undertake at least two of the projects involving consumer products. (These happen to be projects 5-8.) As a result, what are the revised project portfolio and the revised maximum profit?
Expense Scientists Profit ($000) Project Required ($00) 60 36 110 9. 82 53 8. 29 147 4 16 192 56 185 6. 61 173 48 165 8. 2.
Step by Step Solution
3.42 Rating (165 Votes )
There are 3 Steps involved in it
Company TE has eight major projects The company cannot work on all the projects due to constraints o... View full answer