Question: For the following problem, manually construct a project network, activity float chart, and crashing table. List and box the answers to the following questions: (36

For the following problem, manually construct a project network, activity float chart, and crashing table. List and box the answers to the following questions: (36 pts) a. What is the critical path time? b. What is the critical path? c. What is the normal cost to complete the project? d. What is the cost to crash the network by 5 weeks? (Show the crashing cost schedule.) e. What is the cost of crashing to the max? (Use QM to determine the answer.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts