Question: For the following project: Activity (A) Predecessor (--) Normal (4 days) Crash days (3) Crash Cost/day ($500) Activity (B) Predecessor (A) Normal (6 days) Crash
For the following project:
Activity (A) Predecessor (--) Normal (4 days) Crash days (3) Crash Cost/day ($500) Activity (B) Predecessor (A) Normal (6 days) Crash days (4) Crash Cost/day ($300) Activity (C) Predecessor (A) Normal (5 days) Crash days (3) Crash Cost/day ($250) Activity (D) Predecessor (B,C) Normal (8 days) Crash days (5) Crash Cost/day ($700) Activity (E) Predecessor (B) Normal (6 days) Crash days (4) Crash Cost/day ($600) Activity (F) Predecessor (E,D) Normal (7 days) Crash days (5) Crash Cost/day ($550) Activity (G) Predecessor (F) Normal (2 days) Crash days (1) Crash Cost/day ($1000)
Calculate how much it would cost to crash this projectfor every plausible crashing plan
Please make a graph of project length vs. cost