Question: For the following project: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (Weeks) Weeks) Predecessor A 4 3 2,000 2,100 B 2
For the following project: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (Weeks) Weeks) Predecessor A 4 3 2,000 2,100 B 2 1 2,200 2,800 C 3 3 500 500 D 8 16 2,300 2,600 E 3 900 1,200 AB IF 3 3,000 4,200 C G 4 2 1,400 2,000 D, E How much will the cost increase if it is crashed maximum? 1200 1075 1000 1100 900