Question: For the following project: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (Weeks) Weeks) Predecessor A 4 3 2,000 2,100 B 2

For the following project: Activity Normal Time Crash Time Normal Cost Crash

For the following project: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (Weeks) Weeks) Predecessor A 4 3 2,000 2,100 B 2 1 2,200 2,800 C 3 3 500 500 D 8 16 2,300 2,600 E 3 900 1,200 AB IF 3 3,000 4,200 C G 4 2 1,400 2,000 D, E How much will the cost increase if it is crashed maximum? 1200 1075 1000 1100 900

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!