Question: For the following project shown in the table below, SOLVE to answer the questions; (i) Is Mr. A ever scheduled to work more than eight

For the following project shown in the table below, SOLVE to answer the questions;
(i) Is Mr. A ever scheduled to work more than eight hours in a day? Which day(s)?
(ii) What day(s) are Mr. Bs lightest work days on this project?
(iii) How many hours per day is Mr. A scheduled to work during the 10th day of the project?
(iv) How can you minimize the variability in resource consumption?
Activity Precedent Activity Duration (Days) A 6 None None None B 3 4 D Resources (Mr. A, Mr. B) Hours / Day (4,0) (0, 2) (3,6) (0,5) (6,5) (4,4) (0,4) (1, 2) (6,8) A 3 E B N B 6 F G 4 H DF E, G, H 2 2 I 5Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts