Question: For the following sitution draw a PERT network, and determine the following: a- Critical path b- ES,LS,EF,LF and slack time for each activity Minimum expected
For the following sitution draw a PERT network, and determine the following:
a- Critical path
b- ES,LS,EF,LF and slack time for each activity
Minimum expected completion time | Crashing cost/day $$ | Pessimistic time | Most probabl time | Optimistic time | Immediate predecessor(s) | Activity |
1 | 900 | 1 | 1 | 1 |
| A |
2 | 400 | 8 | 6 | 3 | A | B |
3 | 700 | 6 | 5 | 4 | A | C |
3 | 800 | 4 | 3 | 2 | A | D |
|
| 15 | 9 | 9 | A | E |
5 | 300 | 8 | 8 | 7 | B | F |
3 | 500 | 9 | 7 | 4 | B | G |
3 | 700 | 9 | 3 | 1 | C | H |
|
| 7 | 6 | 5 | D | I |
2 | 1100 | 8 | 4 | 3 | F,G,H | J |
3 | 650 | 7 | 3 | 2 | H,I | K |
4 | 300 | 8 | 7 | 7 | H,I | L |
|
| 15 | 9 | 8 | D | M |
7 | 1400 | 17 | 15 | 10 | M | N |
4 | 600 | 9 | 6 | 3 | M | O |
7 | 550 | 13 | 12 | 6 | D | P |
4 | 980 | 12 | 9 | 8 | M | Q |
|
| 7 | 6 | 3 | P,Q | R |
|
| 12 | 8 | 7 | O,R | S |
5 | 520 | 12 | 7 | 6 | J,K,L,N | T |
|
| 5 | 5 | 4 | J,K | U |
1 | 100 | 2 | 2 | 2 | J,K | V |
|
| 9 | 6 | 5 | E,S,T,U,V | W |
3 | 650 | 10 | 10 | 9 | E,S,T,U,V | X |
2 | 50 | 6 | 4 | 3 | W | Y |
4 | 250 | 9 | 8 | 7 | X,Y | Z |
c- Probability to complete the project in 8 days plus the calculated expected completion time or less.
d- Given the answers obtained in parts a and b, suppose the project has fixed costs per day of $1000. Also suppose you could reduce the length of the projects duration by expediting certain activitys expected time at a given cost shown in the table above to some minimum number of days, what would you recommend?((( i need the solution by hand please)))
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock