Question: For the given model, Find Critical Path & Project Duration of the problem Group of answer choices A-C-E-G-H, 13 A-C-E-G-H, 15 Neither of the answers

For the given model,

Find Critical Path & Project Duration of the problem

Group of answer choices

A-C-E-G-H, 13

A-C-E-G-H, 15

Neither of the answers are correct.

A-B-D-G-H, 15

A-B-D-G-H, 13

A-C-F-H, 13