Question: For the given problem, Normal Crash Time Time Task Predecessor Normal Cost Crash Cost (days) (days) . 3 2 40 120 B 7 5 30

For the given problem, Normal Crash Time Time

For the given problem, Normal Crash Time Time Task Predecessor Normal Cost Crash Cost (days) (days) . 3 2 40 120 B 7 5 30 80 AB 5 4 45 90 D A 6 5 30 50 E B, C 4. 2 40 100 F. DE 5 4 55 75 Answer the following questions: a. What is the normal cost of the project? (Select] b. What is the length of the project? (Select ] c. Which activity would you crash first to reduce the project by one day and what will be the cost to crash? (Select] d. Which activity would you crash next by an additional day and what would be the total 2 day cost of crashing? (Select]