Question: For the given project information, please draw the precedence diagram, conduct forward and backward pass calculation, complete the diagram with schedule and float information (

For the given project information, please draw the precedence diagram, conduct forward and backward pass calculation, complete the diagram with schedule and float information (ES,EF, LS,LF, TT, FF), then highlight the critical path.
\table[[Activity,Duration,IPA],[A,6,],[B,2,A],[C,8,A],[D,5,A, B],[E,3,B],[F,6,D, E],[G,5,C, D],[H,2,G],[I,4,G, F],[J,2,H, I]]
Please use the following node notation for the precedence diagram, and upload the finish diagram in the below box.
\table[[ES,TF,EF],[Activity (Duration)],[LS,FF,LF]]
For the given project information, please draw

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!