Question: For the given project, only 10 resources are available: reschedule the project by resource leveling. Try to make the total resources demand each equal to

For the given project, only 10 resources are
For the given project, only 10 resources are available: reschedule the project by resource leveling. Try to make the total resources demand each equal to 10 after leveling. Do not change activity durations. Late project penalty will be 500JD per day. How much would you pay for penalty? Activity Depends on Duration Workers/day A 4 9 B 3 2 2 6 D 2 4 E B 3 8 F 7 2 3 G DF 2 H E,G 4 1