Question: For the house development detailed in Project 1 , you are required to produce a construction schedule in the following formats: a critical path analysis
- For the house development detailed in Project 1, you are required to produce a construction schedule in the following formats:
- a critical path analysis
- a Gantt chart (bar chart)
Your initial planning must include the following:
- list of tasks
- duration of each task
- start and end dates
Define the critical path for the project and determine the shortest construction time in weeks.
| List of Tasks | Start Date | End Date | Duration of Each |
| Demo Prep | 7/06/2023 | 12/06/2023 | 5 |
| Demolition | 13/06/2023 | 26/06/2023 | 13 |
| Excavation | 27/06/2023 | 2/07/2023 | 5 |
| Concrete | 3/07/2023 | 13/07/2023 | 10 |
| Pre backfill | 14/07/2023 | 16/07/2023 | 2 |
| Framing | 27/06/2023 | 6/08/2023 | 40 |
| Roof | 21/07/2023 | 11/08/2023 | 20 |
| Plumbing | 1/07/2023 | 11/08/2023 | 41 |
| Windows | 24/07/2023 | 13/08/2023 | 20 |
| HVAC 3 | 31/07/2023 | 20/08/2023 | 20 |
| Electrical | 10/08/2023 | 20/08/2023 | 10 |
| A/V | 10/08/2023 | 15/08/2023 | 5 |
| House wrap | 5/08/2023 | 9/08/2023 | 4 |
| Insulation | 4/08/2023 | 20/08/2023 | 16 |
| Drywall | 4/09/2023 | 24/08/2023 | 20 |
| Exterior stone | 4/09/2023 | 19/09/2023 | 15 |
| Exterior case | 5/09/2023 | 15/09/2023 | 10 |
| Laundry/furnace | 19/10/2023 | 9/11/2023 | 21 |
| Hardwoods | 20/09/2023 | 9/11/2023 | 50 |
| Tile | 1/11/2023 | 11/11/2023 | 10 |
| Cabinets | 19/09/2023 | 3/11/2023 | 45 |
| Plumbing -hang | 19/10/2023 | 26/10/2023 | 7 |
| Interior doors | 28/10/2023 | 9/11/2023 | 12 |
| Millwork | 18/10/2023 | 20/10/2023 | 2 |
| Interior painting | 31/10/2023 | 15/11/2023 | 45 |
| Stone Counters | 21/11/2023 | 1/12/2023 | 10 |
| Schedule Buffer | 31/10/2023 | 10/11/2023 | 10 |
| Decks | 31/10/2023 | 18/11/2023 | 18 |
| Interior doors hang | 3/01/2024 | 13/01/2024 | 10 |
| Appliances | 2/01/2024 | 3/01/2024 | 1 |
| Plumbing | 2/01/2024 | 5/01/2024 | 3 |
| Electrical | 3/01/2024 | 11/01/2024 | 8 |
| Bathroom Glass | 9/01/2024 | 13/01/2024 | 4 |
| Garage Door | 13/01/2024 | 18/01/2024 | 5 |
| Inspections | 2/01/2024 | 3/01/2024 | 1 |
| Wrap up | 9/01/2024 | 5/02/2024 | 27 |
| Complete | 6/02/2024 | 6/02/2024 | 0 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Critical Path Analysis for House Development Project 1 Demo Prep 5 weeks 2 Demolition 13 weeks 3 Exc... View full answer