Question: For the input in the table below: Draw the network Identify the critical path Calculate the earliestlatest starting and finishing times for each activity Title
For the input in the table below:
Draw the network
Identify the critical path
Calculate the earliestlatest starting and finishing times for each activity
| Title | Activity (A) | Duration (D) | Earliest Start (ES) | Earliest Finish (EF) | Latest Start (LS) | Latest Finish (LF) |
| Sum of longest Predecessors D | Expected D+ES | CP-(expected D +Sum of longest Successors D) | CP- sum of longest Successors D | |||
| A | 1-2 | 4 | ||||
| B | 1-3 | 3 | ||||
| C | 2-4 | 2 | ||||
| D | 2-5 | 7 | ||||
| E | 3-5 | 6 | ||||
| F | 4-6 | 4 | ||||
| G | 5-6 | 2 | ||||
| For calculating LF for each event: | ||||||
| Start from the end and move to the left | ||||||
| Any activity (arrow) going to the end event (circle) equals to the CP | ||||||
| Any other activity (arrow) must be the CP minus the sum of longest successor activities | ||||||