Question: For the input in the table below: Draw the network Identify the critical path Calculate the earliestlatest starting and finishing times for each activity Title

For the input in the table below:

Draw the network

Identify the critical path

Calculate the earliestlatest starting and finishing times for each activity

Title Activity (A) Duration (D) Earliest Start (ES) Earliest Finish (EF) Latest Start (LS) Latest Finish (LF)
Sum of longest Predecessors D Expected D+ES CP-(expected D +Sum of longest Successors D) CP- sum of longest Successors D
A 1-2 4
B 1-3 3
C 2-4 2
D 2-5 7
E 3-5 6
F 4-6 4
G 5-6 2
For calculating LF for each event:
Start from the end and move to the left
Any activity (arrow) going to the end event (circle) equals to the CP
Any other activity (arrow) must be the CP minus the sum of longest successor activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!