Question: For the master production schedule below, develop a labor capacity plan for work centers 1, 2, and 3 using the data provided below in a

For the master production schedule below, develop a labor capacity plan for work centers 1, 2, and 3 using the data provided below in a "rough cut" review method. (12 points) MPS Units Product Period-1 Period-2 Period-3 AA 6 7 6 BB 5 9 4 CC 8 7 7 Direct labor time per end product unit: Product Labor time AA 1 hr BB 2 hrs CC 3 hrs Historical percentages of total hours worked in each work center: Product Usage WC1 50% WC2 30% WC3 20% Total labor hours needed in each period Period-1 Period-2 Period-3 Work center Period-1 Period-2 Period-3 WC1 WC2 WC3 TOTAL