Question: for the network below with all times indicating weeks, answer the following questions and justify your answers ( show your work ) a ) identify

for the network below with all times indicating weeks, answer the following questions and justify your answers (show your work) a) identify the critical path b) if activity D slips by one week, how will the slack in activity G be impacted? c) if activity K can somehow be compressed from six weeks to two weeks, perhaps by adding a significant number of resources, what will be the impact,if any, on the end date of the project?