Question: For the network below with all times indicating weeks, answer the following questions and justify your answers: a . What is the impact on the
For the network below with all times indicating weeks, answer the following questions and justify your
answers:
a What is the impact on the end date of the project if activity I slips by four weeks?
b By how many weeks can activity E slip before the project end date gets extended?
c If activity A slips by one week, how will the slack in activity D be impacted?
d If activity H can somehow be compressed from seven weeks to one week, perhaps by adding a
significant number of resources, what will be the impact, if any, on the end date of the project?