Question: For the network diagram below, complete the following statement by filling in the blanks: This network diagram has ____ (integer) different activity paths. The longest

For the network diagram below, complete the following statement by filling in the blanks:

This network diagram has ____ (integer) different activity paths. The longest duration of these paths is _____ (integer) days. This critical path includes the tasks ______ (format of X,Y,Z etc.).For the network diagram below, complete the

3 days D 2 days E 1 day Kickoff Done! B A 1 day F 1 day G 4 days L O days 1 day H 2 days 2 days 2 days 1 day