Question: For the PERT problem find the critical path and project duration. What is the probability that the project will be completed in 25 days? Activity

For the PERT problem find the critical path and project duration. What is the probability that the project will be completed in 25 days? Activity Predecessor Pessimistic 14 12 - IQTMOOD Optimistic 2 1 0 1 3 3 A C D B E,F G Time Most likely 5 10 0 4 10 5 2 10 6 |@||@ ||~|
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
