Question: Construct a project network with the following precedence relationships: Activity Predcessors Duration Optimistic Most Likely Pessimistic A None 3 4 11 B A 2 5
Construct a project network with the following precedence relationships:
| Activity |
Predcessors | Duration | ||
| Optimistic | Most Likely | Pessimistic | ||
| A | None | 3 | 4 | 11 |
| B | A | 2 | 5 | 8 |
| C | A | 3 | 6 | 9 |
| D | B, C | 8 | 12 | 20 |
| E | B | 3 | 5 | 12 |
| F | D | 2 | 4 | 7 |
| G | C | 6 | 9 | 14 |
| H | E, F, G | 1 | 2 | 4 |
- Check the consistency of your network.
- Find the critical path and project duration of this project.
- Determine the probability of completing the project 2 days earlier.
- Determine the sequence of activities that constitute the second and third critical paths, that is, the paths of the second and third longest duration.
- Based on the first, second and third critical paths determine the four most critical activities. Explain your reasons for choosing these four activities.
- Find a time, say x, such that the probability of project completion time exceeding x
is less than approximately 0.10.
- If the total available resources for this network are 3 units and the resources required for activities A through H are as follows:
| Activity | Resources Required |
| A | 2 |
| B | 1 |
| C | 2 |
| D | 1 |
| E | 1 |
| F | 2 |
| G | 1 |
| H | 1 |
- Find the duration to complete all activities using the ACTIM approach.
- Find the duration to complete all activities using ACTRES approach.