Question: For the project activity parameters given in Table 1 , create an Activity on Node ( AON ) scheduling network diagram. 2 . Create an
For the project activity parameters given in Table create an Activity on Node AON scheduling network diagram. Create an Activity on Arrow AOA scheduling network diagram. Comparing the two networks, which one appears less cluttered and easier to follow? Calculate the Critical Path Method CPM times for each activity Earliest Start, Earliest Finish, Latest Start, and Latest Finish Determine the total slack for each activity. Show your work. What is the critical path of this project? What is the project duration time?