Question: For the project below, create the P 6 schedule and submit the followings: P 6 file ( XER File ) Gantt chart in PDF format

For the project below, create the P6 schedule and submit the followings:
P6 file (XER File)
Gantt chart in PDF format
Network diagram in PDF format
Activity Activity
Number
Durations
(Working Days)
Activities Immediately
Preceding
Start 100-------
Grading 20710
Granular Fill 302110
Electric run-in 404210
Procure metal building 502810
Excavate butane 601720
Compressor foundation 70820
Electrical to compressor 802040
Butane storage 903460
Connect cooling 1001130,70
Bolts and Plates 110630,70
Slab and footings 1201430,70
Piping station 1301590,100
Set compressor 14013110,120
Erect building 1502950,120
Set control panel 1601480,140
Wire building 17017150
Connect piping 18010130,160
Test and clean 1904170,180
Contingency 2005190

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!