Question: for the project? Consider the project depicted in figure below. Based on the information provided, which activity can you delay by one day without impacting


for the project? Consider the project depicted in figure below. Based on the information provided, which activity can you delay by one day without impacting the expected completion date O A. Activity A B. Activity B O C. Activity C O D. Activity D B LS LF 8 days ES EF A D LS LF LS LF 2 days 4 days ES EF ES EF C Activate Window Go to Settings to active\f